The scope of the work of this contract consists of replacing the existing wastewater pump station with a new submersible style pump station to improve the capacity of the sewer system at that location. Main activities related to this project are as follows:
• Installation of a 460 gpm submersible pump system
• Installation of a valve chamber
• Installation of a wet well
• Upgrade the electrical service for pump station to 3 phase/480V
• Paving restoration in the affected areas