Fenwick Street Roadway Resurfacing

  1. Project Overview
  2. Project Update

The existing condition of the roadway surface on Fenwick Street requires that the existing pavement be removed prior to paving.  The damaged asphalt will be removed to a depth of 4 inches.  Then, new asphalt will be installed in 2 lifts: a binder course (usually at 3 inches deep), followed by a 1-inch top course.  Castings are then raised to grade.

Drainage improvements are also being made prior to paving.